City of Virginia Beach, VA
Public Works
Capital Project Detail Sheet

2.088.000: West Neck Road Phase IV

Description and Scope
CIP Section:   Roadways
CIP Status:   Approved Active
Project Type:   New Facility Construction/Expansion
First Year in CIP:  
Business Area:  
  
City District(s):   Princess Anne

This project is for the design and construction of a two-lane undivided parkway from Kellam High School to the end of the curve adjacent to the Fountain property, a distance of 5,750 feet. This project will provide paved shoulders for cyclists, pedestrian accommodations and drainage swales.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager¬†¬† Public Works  Laurie E Murphy P.E. (757)-385-4131

Schedule of Activities
CodeDescription Approved Budget StartApproved Budget EndApproved Budget Cost Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
2000 Design 07/01/2017 09/30/2019 847,690 06/29/2017 10/03/2019 847,690
3000 Site Acquisition 08/01/2018 02/28/2019 2,000,000 08/08/2018 02/28/2019 2,000,000
4000 Private Utility Adjustments 03/01/2019 09/30/2019 333,000 03/01/2019 09/30/2019 333,000
5000 Construction 10/01/2019 11/30/2020 6,660,000 10/01/2019 11/30/2020 6,660,000
6000 Street Lights 12/01/2020 03/31/2021 230,000 12/01/2020 03/31/2021 230,000
7000 Landscaping 04/01/2021 07/31/2021 333,000 04/01/2021 07/01/2021 333,000
9000 Contingencies 07/01/2017 07/31/2021 1,560,554 07/01/2017 07/01/2021 1,560,554
OverallProject Start, End & Cost:07/01/201707/31/202111,964,24406/29/201707/01/202111,964,244

Map for West Neck Road Phase IV
Current Status and Progress
The 90% design was submitted on September 25, 2019. Comments have been received and a Comment Resolution Meeting will be scheduled.
Last updated: 12/03/2018 11:08:33 AM

Attachments
20180404-PWD-515-WestNeckRdPhaseIV-CIP 2-088CitizenNotificationLtr   (50.60 KB pdf)
20180404_CitizenInformationMeetingwithMapFinal slc edits   (206.63 KB pdf)
Animation   (0.53 KB x-mswebsite)

Related Projects