This project is for construction of Elbow Road from Indian River Road to Dam Neck Road at the amphitheater. The typical section will include a four-lane divided highway, with landscaping and aesthetic design features for a length of approximately two and a half (2.5) miles. This project will also include replacement of the existing sub-standard Elbow Road Bridge.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager   Public Works  Annette B Hare P.E. (757)-385-4131
Site Acquisition Manager   Public Works  Gail E Salmons (757)-385-4131
Department Contact   Public Utilities  Algen Canonizado (757)-385-4631
Department Contact   Public Works  Katie E Shannon P.E. (757)-385-4131

Schedule of Activities
CodeDescription Approved Budget StartApproved Budget EndApproved Budget Cost Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
2000 Design 12/01/2016 06/30/2019 6,653,000 07/24/2017 11/19/2018 6,785,000
3000 Site Acquisition 03/01/2006 06/30/2019 4,782,000 03/10/2006 06/28/2019 8,950,000
4000 Private Utility Adjustments 01/01/2019 06/30/2019 500,000 01/01/2019 06/30/2019 500,000
5000 Construction 07/01/2019 07/15/2021 25,300,000 07/02/2019 07/01/2021 25,360,500
6000 Street Lights 01/01/2021 07/15/2021 305,000 01/01/2021 07/01/2021 335,500
7000 Landscaping 01/01/2021 04/30/2021 440,000 01/01/2021 04/01/2021
9000 Contingencies 03/01/2006 07/15/2021 1,899,000 03/10/2006 07/01/2021 3,568,000
OverallProject Start, End & Cost:03/01/200607/15/202139,879,00003/10/200607/01/202145,499,000

Map for Elbow Road Extended Phase II-B
Current Status and Progress
Elbow IIB re-design services underway. Acquisition is in progress.
Last updated: 10/31/2017 12:24:35 PM

Attachments
Phasing Alternative Exhibit   (2.83 MB pdf)

Related Projects
2.065.000   Elbow Road Extended - Phase II-A
2.256.000   Indian River Road Phase VII-A
5.148.000   Elbow Road Ext. Water Improvements Phases I & II (VDOT)