2.156.000: Laskin Road Phase I-B (VDOT)

Description and Scope
CIP Section:   Roadways
CIP Status:   Approved Active
Project Type:   New Facility Construction/Expansion
First Year in CIP:   1991-1992
Business Area:  
  
City District(s):   Beach, Lynnhaven

This project is for construction of an eight-lane divided highway, including bike path and sidewalk, from Republic Road to Winwood Drive, and a six-lane divided highway from Winwood Drive to South Oriole Road, a distance of approximately 2.1 miles. These limits include the intersections at First Colonial Road and at Birdneck Road. Project environmental studies will encompass the entire corridor, from Route 44 to Pacific Avenue, a distance of approximately 3.5 miles. This project was reinstated in the FY 1997-98 CIP.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager¬†¬† Public Works  William C Haggerty (757)-385-4131

Schedule of Activities
CodeDescription Approved Budget StartApproved Budget EndApproved Budget Cost Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
1000 Inspections and Support 07/01/2011 04/01/2022 07/01/1995 06/01/1999
2000 Design 07/01/1995 07/01/2022 6,881,000 07/01/1997 04/01/2015 6,631,000
2100 Study Only 07/01/2014 09/30/2015
3000 Site Acquisition 07/01/1997 10/31/2011 24,306,014 05/01/2002 07/01/2008 25,706,014
4000 Private Utility Adjustments 09/30/2013 12/30/2015 2,826,486 09/01/2013 12/01/2015 3,588,986
5000 Construction 07/01/2023 07/31/2026 15,434,460 07/01/2020 07/01/2025 54,915,795
6000 Street Lights 08/01/2026 11/01/2026 696,705 08/01/2025 10/30/2025 1,646,705
7000 Landscaping 11/02/2026 02/01/2027 378,440 11/01/2025 01/30/2026 1,347,500
9000 Contingencies 07/01/1995 02/01/2027 4,951,310 07/01/1993 02/01/2026 9,386,000
OverallProject Start, End & Cost:07/01/199502/01/202755,474,41507/01/199302/01/2026103,222,000

Map for Laskin Road Phase I-B (VDOT)
Current Status and Progress
This is a VDOT managed project. Right-of-Way acquisition is complete. Dominion Power is currently relocating overhead lines. VDOT is planning Public Hearing for late Summer/early Fall.
Last updated: 06/23/2017 05:11:22 PM

Attachments

Related Projects
2.072.000   First Colonial Rd & VA. Beach Blvd. Intersection Imp.
5.207.000   Laskin Road Water Improvements Phase I (VDOT)
6.075.000   Laskin Road Sewer Improvements Phase I (VDOT)