City of Virginia Beach, VA
Public Works
Capital Project Detail Sheet

2.165.000: Laskin Road Phase II

Description and Scope
CIP Section:   Roadways
CIP Status:   Approved Inactive
Project Type:   New Facility Construction/Expansion
First Year in CIP:   1992-1993
Business Area:  
  
City District(s):   Beach, Lynnhaven

First Cities Project VDOT #14601. This project is for construction of a six-lane divided highway with a bikeway from the eastern terminus of Laskin Road Phase I (in the vicinity of Oriole Drive) to the proposed 30th/31st Street split within a 150' right-of-way, a distance of approximately 0.4 miles.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager¬†¬† Public Works  Christopher J Wojtowicz P.E. (757)-385-4131

Schedule of Activities
CodeDescription Approved Budget StartApproved Budget EndApproved Budget Cost Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
1000 Inspections and Support 07/01/2010 06/30/2019 07/15/2010 06/30/2019 268,903
2000 Design 07/01/2008 07/01/2025 1,118,903 07/01/2017 10/01/2020 850,000
3000 Site Acquisition 07/01/2023 06/30/2024 593,000 01/01/2019 12/31/2019 593,000
4000 Private Utility Adjustments 07/01/2024 07/01/2025 729,135 01/01/2018 06/30/2020 729,135
5000 Construction 07/02/2025 07/01/2026 7,655,920 07/01/2020 07/31/2022 7,291,352
6000 Street Lights 07/02/2026 10/01/2026 126,000 08/01/2022 04/30/2023 126,000
7000 Landscaping 10/02/2026 01/02/2027 364,568 09/01/2022 11/30/2022 364,568
9000 Contingencies 07/01/2008 01/02/2027 1,425,701 08/01/2011 05/30/2017 1,425,701
OverallProject Start, End & Cost:07/01/200801/02/202712,013,22707/15/201004/30/202311,648,659

Map for Laskin Road Phase II
Current Status and Progress
Design is 30% complete. Project is requested but only partially funded in the current CIP. No further activity on this project
Last updated: 01/20/2017 08:29:42 AM