City of Virginia Beach, VA
Public Works
Capital Project Detail Sheet

2.117.000: Shore Drive Corridor Improvements Phase III

Description and Scope
CIP Section:   Roadways
CIP Status:   Approved Active
Project Type:   New Facility Construction/Expansion
First Year in CIP:   2006-2007
Business Area:  
  
City District(s):   Lynnhaven

This project begins at Vista Circle, near the eastern end of the Lesner Bridge, and extends eastward through the Great Neck Road intersection and terminates at Croix Drive. This project will improve vehicular and pedestrian traffic flow and safety in the roadway and intersections; improve storm drainage; include a multi-use trail, 5-ft sidewalk and on-street bike lanes; and enhance the corridor with aesthetic elements such as landscaping and lighting.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager¬†¬† Public Works  William M. Purcell (757)-385-4131

Schedule of Activities
CodeDescription Approved Budget StartApproved Budget EndApproved Budget Cost Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
2000 Design 06/20/2011 07/31/2019 2,321,109 06/20/2011 03/01/2019 2,530,584
3000 Site Acquisition 01/01/2018 02/15/2019 2,484,453 01/01/2018 12/01/2019 4,176,976
4000 Private Utility Adjustments 02/01/2019 07/31/2019 1,000,000 09/01/2018 12/01/2019 1,652,350
5000 Construction 08/01/2019 08/15/2022 15,459,672 12/31/2019 12/31/2022 16,523,503
6000 Street Lights 08/15/2022 11/15/2022 689,665 12/31/2022 03/31/2023 689,665
7000 Landscaping 11/15/2022 02/28/2023 166,644 12/31/2022 03/31/2023 166,644
9000 Contingencies 06/01/2011 02/28/2023 2,278,875 06/20/2011 03/31/2023 1,737,981
OverallProject Start, End & Cost:06/01/201102/28/202324,400,41806/20/201103/31/202327,477,703

Map for Shore Drive Corridor Improvements Phase III
Current Status and Progress
100% design is under review.
Last updated: 01/15/2019 07:12:06 AM