2.401.000: Greenwich Rd Crossover & Cleveland St Improvements

Description and Scope
CIP Section:   Roadways
CIP Status:   Approved Active
Project Type:   New Facility Construction/Expansion
First Year in CIP:   2010-2011
Business Area:  
  
City District(s):   Kempsville

VDOT #264-134-102 project will realign Greenwich Road and connect it to Cleveland Street by a bridge structure over I-264. However, VDOT relocated Greenwich Road ends at the Cleveland Street/Clearfield Avenue intersection. This City project will acquire the necessary right-of-way and easements for the VDOT's Greenwich Road crossover and the design and construction for the three phases of the Cleveland Street improvements from the Clearfield Avenue intersection to the Witchduck Road intersection. The first phase includes installing a box culvert in the existing open channel and constructing the fourth leg of the Clearfield Avenue/Cleveland Street intersection. The second phase involves relocating the existing Clearfield Avenue/Cleveland Street intersection. The third phase will improve Cleveland Street from Clearfield Avenue intersection to the Witchduck Road intersection.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager   Public Works  Norbert R Kuhn P.E. (757)-385-4131
Department Contact   Public Works  Chris B Cahoon (757)-385-4131

Schedule of Activities
CodeDescription Approved Budget StartApproved Budget EndApproved Budget Cost Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
2000 Design 07/01/2010 12/31/2016 1,067,535 07/01/2010 07/31/2017 1,004,045
3000 Site Acquisition 07/01/2010 07/31/2017 2,534,426 07/01/2010 12/31/2017 4,780,000
4000 Private Utility Adjustments 07/01/2014 07/31/2017 908,568 07/01/2014 12/31/2017 945,568
5000 Construction 10/31/2014 05/31/2018 10,393,495 09/26/2014 05/31/2018 7,103,495
6000 Street Lights 01/30/2015 06/30/2018 397,500 01/01/2015 06/30/2018 530,000
7000 Landscaping 01/30/2015 06/30/2018 315,795 01/01/2015 06/30/2018 315,795
9000 Contingencies 07/01/2010 08/31/2018 1,142,681 07/01/2010 08/31/2018 1,584,847
OverallProject Start, End & Cost:07/01/201008/31/201816,760,00007/01/201008/31/201816,263,750

Map for Greenwich Rd Crossover & Cleveland St Improvements
Current Status and Progress
This project is broken into 4 phases. (Phase 1A, 1B, 2 & 3) Also, this project will fund the bridge aesthetics for the Greenwich Road Flyover. The construction is completed on Phase 1A. On Phase 1B and Phase 2, the design is approximately 100% completed and one remaining parcel is left on the site acquisition. On Phase 3, a typical section was selected by the study that was prepared by KHA. KHA is preparing the scope and fee proposal to complete the design services for Phase 3. The "Current Estimates" reflects all the phases of the project. The "Approved Budget" only funded Phase 1A, 1B, & 2 and the design services for Phase 3.
Last updated: 06/09/2017 09:54:55 AM