2.178.027: Providence Road Pedestrian Improvements

Description and Scope
CIP Section:   Roadways
CIP Status:   Inactive
Project Type:   Renovation/Rehabilitation
First Year in CIP:  
Business Area:  
  
City District(s):   Centerville, Kempsville

This project includes the installation of new sidewalk along the north side of Providence Rd. from Whitehurst Landing Ave. to Beryl Ave. as well as pedestrian signal improvements at the intersection of Providence & Beryl.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager   Public Works  Completed Roadway Project (757)-385-4131
Department Contact   Public Works  Annette B Hare P.E. (757)-385-4131

Schedule of Activities
CodeDescription Approved Budget StartApproved Budget EndApproved Budget Cost Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
2000 Design 07/01/2012 07/26/2013 80,000
4000 Private Utility Adjustments 08/01/2013 02/28/2014 29,000
5000 Construction 06/30/2014 11/19/2014 365,000
9000 Contingencies 01/02/2012 11/01/2014 26,000
OverallProject Start, End & Cost:  01/02/201211/19/2014500,000

Map for Providence Road Pedestrian Improvements
Current Status and Progress
Project is complete.
Last updated: 12/31/2014 11:40:28 AM