2.025.000: Witchduck Road Phase II

Description and Scope
CIP Section:   Roadways
CIP Status:   Approved Active
Project Type:   New Facility Construction/Expansion
First Year in CIP:   2000-2001
Business Area:  
  
City District(s):   Bayside, Kempsville

First Cities Project, UPC# 55202, VDOT #U000-134-175. This project will provide a six-lane divided roadway on a 143-foot to 165-foot variable right-of-way from I-264 to Virginia Beach Blvd., a distance of approximately 2,600 feet. Aesthetic improvements such as a wide outside lane for cyclists and 16-foot wide benches comprised of brick pavers and sidewalk will be provided to enhance this roadway corridor. Roadway modifications also include Pennsylvania Avenue, Mac Street, Southern Boulevard, Cleveland Street and Admiral Wright Road at Denn Lane.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager   Public Works  William C Haggerty (757)-385-4131
Department Contact   Public Utilities  Edwin Garcia-Cardona (757)-385-4631
Department Contact   Public Works  Katie E Shannon P.E. (757)-385-4131
Department Contact   Public Works  Kristal M Johnson (757)-385-4131

Schedule of Activities
CodeDescription Approved Budget StartApproved Budget EndApproved Budget Cost Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
1000 Inspections and Support 04/01/2015 06/30/2018 300,000 05/02/2016 07/27/2018 300,000
2000 Design 02/01/2004 03/01/2016 2,816,394 02/02/2004 04/22/2016 3,159,498
3000 Site Acquisition 10/13/2013 12/01/2015 23,764,000 10/31/2013 05/20/2016 23,640,649
4000 Private Utility Adjustments 12/03/2015 10/31/2016 827,297 02/06/2015 07/29/2016 1,418,975
5000 Construction 12/01/2016 09/30/2019 25,956,616 01/17/2017 02/01/2020 25,872,449
6000 Street Lights 06/01/2019 09/30/2019 783,836 11/01/2018 02/01/2020 868,003
7000 Landscaping 08/01/2019 09/30/2019 153,836 11/01/2019 02/01/2020 153,836
9000 Contingencies 02/01/2004 09/30/2019 5,460,197 02/02/2004 02/01/2020 4,648,766
OverallProject Start, End & Cost:02/01/200409/30/201960,062,17602/02/200402/01/202060,062,176

Map for Witchduck Road Phase II
Current Status and Progress
Construction contract awarded and contractor began work in January 2017. Work is approximately 24% complete.
Last updated: 10/19/2017 09:58:11 AM

Attachments
12-13-12 Exhibit   (3.45 MB pdf)
12/13 Location and Design Public Hearing Brochure   (517.68 KB pdf)
12/13 Location and Design Public Hearing Comment Sheet   (61.06 KB pdf)
Approved NEPA CE Environmental Document   (186.93 KB pdf)

Related Projects
2.049.001   Witchduck Road/Cleveland Street Intersection Improvement
2.109.000   Pembroke Area Transportation Improvements
2.931.000   Witchduck Road - Phase I (First Cities Project)
6.603.000   Witchduck Rd - Phase I Sewer Improvements
6.604.000   Witchduck Road Phase II Sewer Improvements