2.048.000: Princess Anne Rd./Kempsville Rd. Inter. Impr.

Description and Scope
CIP Section:   Roadways
CIP Status:   Approved Active
Project Type:   New Facility Construction/Expansion
First Year in CIP:   2000-2001
Business Area:  
  
City District(s):   Kempsville

VDOT # 0165-134-107. This project provides funding to study, design, and reconstruct the Princess Anne Road/Kempsville Road/Witchduck Road intersection to raise the capacity of the intersection to meet future demands and eliminate current congestion problems.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager   Public Works  William C Haggerty (757)-385-4131
Site Acquisition Manager   Public Works  Chris B Cahoon (757)-385-4131

Schedule of Activities
CodeDescription Approved Budget StartApproved Budget EndApproved Budget Cost Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
2000 Design 10/01/2000 02/28/2012 4,500,000 10/01/2000 07/01/2010 4,500,000
3000 Site Acquisition 05/01/2007 11/30/2009 48,308,124 05/01/2007 05/14/2010 49,673,124
4000 Private Utility Adjustments 11/01/2009 10/31/2011 4,117,000 03/31/2010 10/31/2011 4,117,000
5000 Construction 12/01/2010 07/31/2014 27,248,297 07/18/2011 12/15/2014 27,248,297
6000 Street Lights 08/01/2014 10/31/2014 470,000 11/30/2014 03/31/2015 470,000
7000 Landscaping 08/01/2014 11/30/2014 1,049,192 09/01/2014 03/31/2015 1,049,192
9000 Contingencies 10/01/2000 11/30/2014 2,978,432 10/01/2000 04/28/2015 3,065,568
OverallProject Start, End & Cost:10/01/200011/30/201488,671,04510/01/200004/28/201590,123,181

Map for Princess Anne Rd./Kempsville Rd. Inter. Impr.
Current Status and Progress
Construction is underway. Project is approximately 85% complete. Work anticipated in the next 60 days includes: curbing, grading and paving at west end of Princess Anne Road, median construction along Kempsville/Witchduck Road, activation of new traffic signal at Witchduck/Bonney/Office Square Lane, and utility work along Singleton Way.
Last updated: 09/11/2014 05:31:37 PM

Attachments
Overall Project Plan   (273.47 KB pdf)
Project Aerial Map   (538.56 KB pdf)

Related Projects
2.931.000   Witchduck Road - Phase I (First Cities Project)