2.116.000: Shore Drive Corridor Improvements - Phase II (Partial)

Description and Scope
CIP Section:   Roadways CIP Status:   Requested - Not Funded Active
Project Type:   Expansion First Year in CIP:  
Business Area:  
City District(s):   Bayside

This project will provide safety improvements, including pedestrian walkways and bikeways, along the Shore Drive corridor from South Oliver Drive/Waterspoint Place to Treasure Island Drive. It will also include improvements along Shore Drive at the Northampton Boulevard interchange and to the intersections at Pleasure House Road and at Greenwell Road.

Points of Contact
Project Manager:   Public Works  David S Jarman P.E. (757)-385-4131

Schedule of Activities
Project ActivityApproved BudgetCurrent Estimates
CodeDescription StartEndCost StartEndCost
2000 Design 07/01/2010 12/31/2013 575,000 07/15/2010 12/16/2013 575,000
3000 Site Acquisition 01/01/2017 01/31/2019 1,082,000 01/16/2017 01/16/2019 1,082,000
4000 Private Utility Adjustments 02/01/2019 02/28/2020 250,000 02/15/2019 02/14/2020 250,000
5000 Construction 03/01/2020 03/31/2021 7,785,000 03/09/2020 03/09/2021 7,785,000
6000 Street Lights 04/01/2021 07/31/2021 300,000 04/15/2021 07/15/2021 300,000
7000 Landscaping 08/01/2021 11/30/2021 600,000 08/16/2021 11/16/2021 600,000
9000 Contingencies 07/01/2010 11/30/2021 1,588,800 06/24/2010 11/17/2021 500,000
Overall Project Start, End & Cost:07/01/201011/30/202112,180,80006/24/201011/17/202111,092,000 

Map for Shore Drive Corridor Improvements - Phase II (Partial)
Current Status and Progress
35% Design was completed under CIP 2-200. Project is requested but not funded under the current CIP.
Last updated: 02/24/2011 02:44:06 PM