2.088.000: West Neck Road Phase IV

Description and Scope
CIP Section:   Roadways
CIP Status:   Approved Active
Project Type:   New Facility Construction/Expansion
First Year in CIP:  
Business Area:  
  
City District(s):   Princess Anne

This project is for the design and construction of a two-lane undivided parkway from Kellam High School to the end of the curve adjacent to the Fountain property, a distance of 5,750 feet. This project will provide paved shoulders for cyclists, pedestrian accommodations, and drainage swales.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager¬†¬† Public Works  Laurie E Murphy P.E. (757)-385-4131

Schedule of Activities
CodeDescription Approved Budget StartApproved Budget EndApproved Budget Cost Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
2000 Design 07/01/2017 06/30/2020 847,690 07/15/2017 01/30/2022 908,300
3000 Site Acquisition 03/01/2020 06/30/2020 2,000,000 07/01/2021 10/30/2021 737,000
4000 Private Utility Adjustments 07/01/2020 09/30/2020 333,000 09/30/2021 01/29/2022 101,540
5000 Construction 10/01/2020 09/30/2021 4,975,450 01/30/2022 03/30/2023 6,917,763
6000 Street Lights 10/01/2021 01/31/2022 303,597 02/01/2023 04/30/2023 481,069
7000 Landscaping 02/01/2022 05/31/2022 79,962 05/01/2023 08/30/2023 78,750
9000 Contingencies 07/01/2017 05/31/2022 826,834 07/15/2017 03/30/2023 701,930
OverallProject Start, End & Cost:07/01/201705/31/20229,366,53307/15/201708/30/20239,926,352

Map for West Neck Road Phase IV
Current Status and Progress
The acquisition of the required properties was completed on 10/5/21. Dominion Energy will be relocating their facilities beginning 11/25/21. The construction documents and plans are being finalized and scheduled to be complete by 11/15/21. The Project Award for the selection of a Contractor is 1/7/22. The Contractor's Notice to Proceed with construction is 2/18/22.
Last updated: 11/12/2021 09:24:58 AM

Attachments
20180404-PWD-515-WestNeckRdPhaseIV-CIP 2-088CitizenNotificationLtr   (50.60 KB pdf)
20180404_CitizenInformationMeetingwithMapFinal slc edits   (206.63 KB pdf)
Animation   (0.53 KB x-mswebsite)

Related Projects