City of Virginia Beach, VA
Public Works
Capital Project Detail Sheet

2.078.000: Sandbridge Road-Nimmo Phase VII-A

Description and Scope
CIP Section:   Roadways
CIP Status:   Approved Active
Project Type:   New Facility Construction/Expansion
First Year in CIP:  
Business Area:  
  
City District(s):   Princess Anne

VDOT UPC #113196. This project is for the construction of Sandbridge Road-Nimmo Parkway Phase VII-A, a two-lane roadway with on-road bike lanes, 10 foot shared use path on the south side, new storm system, and new water lines. The project will also raise the roadway elevation to be passible during the 100 year flood and to account for 3 additional feet of sea level rise. The project corridor is from Sandpiper Road to approximately 1.1 mile west of Sandpiper Road. The project represents the first phase of Nimmo Parkway Phase VII, which has limits from Sandpiper Road to Atwoodtown Road.
This project is for the construction of Nimmo Parkway Phase VII-A, as a two-lane roadway with on-road bike lanes, 10 foot shared use path on the south side, new storm system, and new water lines. The project will also raise the roadway elevation to be passible during the 100 year flood and to account for 3 additional feet of sea level rise. The project corridor is from Sandpiper Road to approximately 1.1 mile west of Sandpiper Road. The project represents the first phase of Nimmo Parkway Phase VII, which has limits from Sandpiper Road to Atwoodtown Road.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager¬†¬† Public Works  Ryan A Johnson (757)-385-4131

Schedule of Activities
CodeDescription Approved Budget StartApproved Budget EndApproved Budget Cost Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
2000 Design 07/01/2014 06/30/2021 1,664,000 07/01/2014 11/01/2021 1,869,211
3000 Site Acquisition 07/01/2020 06/30/2021 325,000 07/01/2021 04/01/2022 325,000
4000 Private Utility Adjustments 07/01/2021 10/31/2023 500,000 09/01/2021 05/01/2022 2,000,000
5000 Construction 10/01/2021 10/31/2023 17,745,000 12/01/2021 12/01/2024 19,301,392
6000 Street Lights 11/01/2023 01/31/2024 669,000 01/01/2024 04/01/2024 669,000
7000 Landscaping 02/01/2024 05/31/2024 364,000 02/01/2024 05/01/2024 364,000
9000 Contingencies 07/01/2014 05/31/2024 1,613,000 07/01/2014 12/01/2024 1,930,139
OverallProject Start, End & Cost:07/01/201405/31/202422,880,00007/01/201412/01/202426,458,742

Map for Sandbridge Road-Nimmo Phase VII-A
Current Status and Progress
Environmental permits for the Army Corp of Engineers and Department of Environmental Quality have been received. Bid plans are currently in development. Private Utility coordination is ongoing. Right-of Way acquisition process is ongoing. NTP for construction anticipated spring/summer 2022.
Last updated: 10/29/2021 09:57:03 AM