City of Virginia Beach, VA
Public Works
Capital Project Detail Sheet

2.078.000: Sandbridge Road-Nimmo Phase VII-A

Description and Scope
CIP Section:   Roadways
CIP Status:   Approved Active
Project Type:   New Facility Construction/Expansion
First Year in CIP:  
Business Area:  
  
City District(s):   Princess Anne

This project is for the construction of Nimmo Parkway Phase VII-A, as a two-lane roadway with on-road bike lanes, 10 foot shared use path on the south side, new storm system, and new water lines. The project will also raise the roadway elevation to be passible during the 100 year flood and to account for 3 additional feet of sea level rise. The project corridor is from Sandpiper Road to approximately 1.1 mile west of Sandpiper Road. The project represents the first phase of Nimmo Parkway Phase VII, which has limits from Sandpiper Road to Atwoodtown Road.
This project is for the construction of Nimmo Parkway Phase VII-A, as a two-lane roadway with on-road bike lanes, 10 foot shared use path on the south side, new storm system, and new water lines. The project will also raise the roadway elevation to be passible during the 100 year flood and to account for 3 additional feet of sea level rise. The project corridor is from Sandpiper Road to approximately 1.1 mile west of Sandpiper Road. The project represents the first phase of Nimmo Parkway Phase VII, which has limits from Sandpiper Road to Atwoodtown Road.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager¬†¬† Public Works  Ryan A Johnson (757)-385-4131

Schedule of Activities
CodeDescription Approved Budget StartApproved Budget EndApproved Budget Cost Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
2000 Design 07/01/2014 07/31/2019 1,596,000 07/01/2014 06/30/2021 1,664,000
3000 Site Acquisition 01/01/2019 10/31/2019 325,000 07/01/2020 06/30/2021 325,000
4000 Private Utility Adjustments 01/01/2019 10/31/2019 500,000 07/01/2021 10/31/2023 500,000
5000 Construction 07/01/2021 06/30/2023 17,528,000 10/01/2021 10/31/2023 17,745,000
6000 Street Lights 07/01/2023 10/31/2023 669,000 11/01/2023 01/31/2024 669,000
7000 Landscaping 11/01/2023 02/28/2024 364,000 02/01/2024 05/30/2024 364,000
9000 Contingencies 07/01/2014 02/28/2024 1,898,000 07/01/2014 05/30/2024 2,127,000
OverallProject Start, End & Cost:07/01/201402/28/202422,880,00007/01/201405/30/202423,394,000

Map for Sandbridge Road-Nimmo Phase VII-A
Current Status and Progress
Environmental permits for the Army Corp of Engineers and Department of Environmental Quality have been received. 90% design plans are currently in development. Private Utility coordination is ongoing
Last updated: 07/20/2020 09:52:15 AM