City of Virginia Beach, VA
Public Works
Capital Project Detail Sheet
2.117.000: Shore Drive Corridor Improvements Phase III
Description and Scope
CIP Section:
Roadways
CIP Status:
Approved
Active
Project Type:
New Facility Construction/Expansion
First Year in CIP:
2006-2007
Business Area:
City District(s):
Lynnhaven
This project begins at Vista Circle, near the eastern end of the Lesner Bridge, and extends eastward through the Great Neck Road intersection and terminates at Croix Drive. This project will improve vehicular and pedestrian traffic flow and safety in the roadway and intersections; improve storm drainage; include a multi-use trail, 5-ft sidewalk and on-street bike lanes; and enhance the corridor with aesthetic elements such as landscaping and lighting.
Points of Contact
Contact Type
Company
Contact Person
Phone
Project Manager
Public Works
William M. Purcell
(757)-385-4131
Schedule of Activities
Code
Description
|
Approved Budget Start
Approved Budget End
Approved Budget Cost
|
Current Estimates Start
Current Estimates End
Current Estimates Cost
2000
Design
06/20/2011
09/30/2020
2,701,644
06/01/2011
12/01/2022
3,095,139
3000
Site Acquisition
01/01/2018
01/31/2021
4,260,516
02/01/2022
06/01/2023
5,097,970
4000
Private Utility Adjustments
07/01/2020
07/31/2021
1,849,745
08/01/2022
08/01/2023
2,000,000
5000
Construction
08/01/2021
02/28/2025
17,092,529
02/01/2024
08/01/2027
28,326,028
6000
Street Lights
03/01/2025
06/30/2025
1,263,490
05/01/2026
08/01/2026
1,263,490
7000
Landscaping
03/01/2025
06/30/2025
141,433
09/01/2026
12/01/2026
141,433
9000
Contingencies
06/01/2011
06/30/2025
1,849,745
06/01/2011
08/01/2027
3,542,400
Overall
Project Start, End & Cost:
06/01/2011
06/30/2025
29,159,102
06/01/2011
08/01/2027
43,466,460
Current Status and Progress
The design is currently being modified to incorporate Virginia Stormwater Management Technical Criteria Part IIB and City review comments from the 100% design submittal. The current schedule will be shifted to account for impacts to City staff and resources resulting from the May 31, 2019 shooting and COVID. The schedule above is not accurate and cannot be updated at this time due to software technical difficulties. Additional design effort and multiple outstanding Real Estate acquisitions required for the project are underway.
Last updated: 02/28/2022 09:43:41 AM