2.126.000: Laskin Road Phase I-A (VDOT)

Description and Scope
CIP Section:   Roadways
CIP Status:   Approved Active
Project Type:   New Facility Construction/Expansion
First Year in CIP:  
Business Area:  
  
City District(s):   Beach, Lynnhaven

This is the second phase of the overall Laskin Road Phase I project. The project includes construction of an 8-lane divided highway (three through lanes and a continuous right turn lane in each direction) from Republic Road to the limits of the Laskin Road Bridge Replacement at Fremac Drive. This phase also includes full improvements to the Laskin Road/First Colonial Road intersection as well as construction of a 6-lane divided highway on First Colonial Road from Laurel Lane to I-264. The feeder roads along Laskin Road within the project limits will be removed with this project. 14-foot wide outside lanes for cyclists and a 10-foot wide shared-use path on one side of the roadway will be provided with a 5-foot wide sidewalk on the other side of Laskin Road. Aesthetic improvements such as a landscaped median and verge areas will enhance the roadway corridor. The roadway will be passable during the 100-year flood event.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager¬†¬† Public Works  William M. Purcell (757)-385-4131

Schedule of Activities
CodeDescription Approved Budget StartApproved Budget EndApproved Budget Cost Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
2000 Design 12/01/2017 10/31/2018 1,170,000 12/01/2017 10/01/2018 1,170,000
3000 Site Acquisition 10/01/2018 01/15/2019 4,992,976 10/01/2018 01/01/2019 4,992,976
4000 Private Utility Adjustments 07/01/1997 01/01/2019
5000 Construction 01/15/2019 05/31/2023 49,616,391 01/01/2019 05/01/2023 49,292,997
6000 Street Lights 01/01/2023 05/31/2023 236,223 01/01/2023 05/01/2023 236,223
7000 Landscaping 01/01/2023 05/31/2023 498,766 01/01/2023 05/01/2023 498,766
OverallProject Start, End & Cost:12/01/201705/31/202356,514,35607/01/199705/01/202356,190,962

Map for Laskin Road Phase I-A (VDOT)
Current Status and Progress
VDOT advertised for construction bids Jan 22, 2019. Contractor bids exceeded budget. VDOT and City of VB identified additional funds to proceed with project. Notice to proceed issued to contractor September 3, 2019. Work in progress with a planned completion of Apr 2023. VDOT project website: https://www.virginiadot.org/projects/hamptonroads/laskin_road.asp
Last updated: 10/26/2021 08:29:10 AM

Attachments
LASKIN ROAD PHASING   (2.78 MB pdf)

Related Projects
2.040.000   Laskin Road Bridge Replacement (VDOT)
2.146.000   Laskin Road Phase III
2.156.000   Laskin Road Phase I-B
2.165.000   Laskin Road Phase II