City of Virginia Beach, VA
Public Works
Capital Project Detail Sheet

2.135.000: Cleveland Street Improvements IV

Description and Scope
CIP Section:   Roadways
CIP Status:   Approved Active
Project Type:   New Facility Construction/Expansion
First Year in CIP:  
Business Area:  
  
City District(s):   Bayside

This project will provide funding for design, property acquisition and construction of an improved Cleveland Street/Columbus Street, 3-lane, 90-foot wide, divided roadway 1.2 miles length between Witchduck Road and Independence Boulevard with turn lanes, shared-use pathways, on-road bike lanes and landscaping as identified in the Pembroke Strategic Growth Area (SGA) Plan.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager¬†¬† Public Works  Christina L. Ammens (757)-385-4131

Schedule of Activities
CodeDescription Approved Budget StartApproved Budget EndApproved Budget Cost Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
2000 Design 07/01/2019 06/30/2023 2,220,000 07/01/2019 12/01/2025 2,635,508
3000 Site Acquisition 01/02/2021 02/01/2023 8,073,000 07/01/2023 07/01/2024 9,299,857
4000 Private Utility Adjustments 07/01/2022 06/30/2023 1,360,000 07/01/2024 07/01/2025 1,360,000
5000 Construction 07/01/2023 12/31/2025 11,099,000 01/01/2026 06/01/2028 12,171,870
6000 Street Lights 07/01/2025 12/31/2025 252,000 07/01/2028 12/01/2028 252,000
7000 Landscaping 09/01/2025 12/31/2025 118,000 09/01/2028 12/01/2028 118,000
9000 Contingencies 07/01/2019 12/31/2025 1,925,000 07/01/2019 06/01/2028 2,583,700
OverallProject Start, End & Cost:07/01/201912/31/202525,047,00007/01/201912/01/202828,420,935

Map for Cleveland Street Improvements IV
Current Status and Progress
Alignment Study performed in 2018. Preliminary design is scheduled to begin in Winter 2021. 30% submittal is scheduled for Spring 2022.
Last updated: 11/15/2021 09:46:07 AM