2.038.000: Rosemont Road Phase V

Description and Scope
CIP Section:   Roadways
CIP Status:   Approved Active
Project Type:   New Facility Construction/Expansion
First Year in CIP:   2013-2014
Business Area:  
  
City District(s):   Centerville, Rose Hall

VDOT UPC #105623. This project is for the construction of a four-lane divided roadway from Primrose Lane/Harbringer Road to Dam Neck Road, a distance of approximately 1.3 miles. The four-lane divided roadway will include a continuous 10-foot wide sidewalk along the east side of the corridor, as well as a 10-foot wide sidewalk along the west side from Faculty Boulevard to Lynnhaven Parkway. This project also includes the upgrade of three existing traffic signals at Buckner Boulevard, Faculty Boulevard/Celtic Drive, and Concert Drive.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager   Public Works  Dustin Kwok (757)-385-4131
Department Contact   Public Utilities  Bernard M. Moran (757)-385-4631

Schedule of Activities
CodeDescription|Approved Budget StartApproved Budget EndApproved Budget Cost|Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
2000 Design 09/01/2014 09/30/2020 1,354,000 09/01/2014 06/15/2022 1,798,724
3000 Site Acquisition 01/01/2017 09/30/2020 2,250,000 04/16/2022 06/14/2023 3,045,020
4000 Private Utility Adjustments 09/01/2020 09/30/2021 850,000 06/15/2023 06/13/2024 892,500
5000 Construction 09/01/2021 03/31/2024 12,275,000 01/16/2025 01/15/2028 13,550,000
6000 Street Lights 09/01/2023 01/31/2024 830,000 09/01/2025 01/31/2026 830,000
7000 Landscaping 01/01/2024 03/31/2024 445,000 01/01/2026 03/31/2026 445,000
9000 Contingencies 09/01/2014 03/31/2024 1,686,000 09/01/2014 01/31/2028 2,318,700
OverallProject Start, End & Cost:09/01/201403/31/202419,690,00009/01/201401/31/202822,879,944

Map for Rosemont Road Phase V
Current Status and Progress
Stormwater design criteria issue resolved. 90% (Pre-Final Design) Submittal received November 2021. Change order pending for utilities design including water and sewer system betterments.
Last updated: 03/02/2022 10:03:27 AM

Attachments
CIM Landscape Board 1   (2.88 MB pdf)
CIM Landscape Board 2   (3.64 MB pdf)
CIM Presentation Layout   (3.57 MB pdf)
CIM Project Info Brochure   (827.19 KB pdf)

Related Projects
2.041.000   Dam Neck Road - Phase I
2.190.005   Rosemont Rd/ Lynnhaven Pkwy Intersection Imp