City of Virginia Beach, VA
Public Works
Capital Project Detail Sheet

2.401.000: Greenwich Rd Crossover & Cleveland St Improvements

Description and Scope
CIP Section:   Roadways
CIP Status:   Approved Active
Project Type:   New Facility Construction/Expansion
First Year in CIP:   2010-2011
Business Area:  
  
City District(s):   Kempsville

VDOT #264-134-102 project will realign Greenwich Road and connect it to Cleveland Street by a bridge structure over I-264. However, VDOT relocated Greenwich Road ends at the Cleveland Street/Clearfield Avenue intersection. This City project will acquire the necessary right-of-way and easements for the VDOT's Greenwich Road crossover and the design and construction for the three phases of the Cleveland Street improvements from the Clearfield Avenue intersection to the Witchduck Road intersection. The first phase includes installing a box culvert in the existing open channel and constructing the fourth leg of the Clearfield Avenue/Cleveland Street intersection. The second phase involves relocating the existing Clearfield Avenue/Cleveland Street intersection. The third phase will improve Cleveland Street from Clearfield Avenue intersection to the Witchduck Road intersection.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager   Public Works  Christina L. Ammens (757)-385-4131
Department Contact   Public Works  Chris B Cahoon (757)-385-4131
Department Contact   Public Works  Norbert R Kuhn P.E. (757)-385-4131

Schedule of Activities
CodeDescription Approved Budget StartApproved Budget EndApproved Budget Cost Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
2000 Design 07/01/2010 12/31/2019 1,225,142 07/01/2010 07/01/2023 1,364,722
3000 Site Acquisition 07/01/2010 03/31/2020 2,819,949 07/01/2010 09/01/2022 2,876,431
4000 Private Utility Adjustments 07/01/2014 07/31/2020 921,014 07/01/2014 07/01/2023 1,261,068
5000 Construction 10/01/2014 12/31/2021 8,810,080 10/01/2014 04/01/2024 8,685,736
6000 Street Lights 01/01/2015 12/31/2021 86,000 01/01/2015 07/01/2023 86,000
7000 Landscaping 01/01/2015 12/31/2021 118,010 01/01/2015 07/01/2023 118,010
9000 Contingencies 07/01/2010 12/31/2021 901,119 07/01/2010 04/01/2024 693,357
OverallProject Start, End & Cost:07/01/201012/31/202114,881,31407/01/201004/01/202415,085,324

Map for Greenwich Rd Crossover & Cleveland St Improvements
Current Status and Progress
This project is broken into 4 phases. (Phase 1A, 1B, 2 & 3). Construction is complete on phases 1A & 1B. Phases 2 & 3 are being tracked under 2.401.002 & 2.401.003.
Last updated: 11/15/2021 09:46:40 AM

Attachments

Related Projects
2.025.000   Witchduck Road Phase II
2.412.000   Cleveland St/Clearfield Ave Intersection Improvements
6.604.000   Witchduck Road Phase II Sewer Improvements