City of Virginia Beach, VA
Public Works
Capital Project Detail Sheet
2.409.000: Centerville Turnpike Phase II
Description and Scope
CIP Section:
Roadways
CIP Status:
Approved
Active
Project Type:
New Facility Construction/Expansion
First Year in CIP:
Business Area:
City District(s):
Centerville, Kempsville
VDOT UPC #103005. City Council identified this project as a Council Initiative under the Goal Improve the Transportation System in the 2018 Annual Report to City Council. This project is for the construction of a four-lane divided highway within a 130 foot right-of-way from Indian River Road to Kempsville Road, a distance of 1.85 miles. This project will provide improvements at the Kempsville Road and Indian River Road intersections, including triple left turn lanes onto Indian River Road from Centerville Turnpike. This project will also include sidewalk, dedicated on-road bike lanes, landscaping, and relocation of existing aerial utilities to a new overhead location.
Points of Contact
Contact Type
Company
Contact Person
Phone
Project Manager
Public Works
Laurie E Murphy P.E.
(757)-385-4131
Department Contact
Public Utilities
Christopher A Johnson P.E.
(757)-385-4631
Department Contact
Public Works
David Perry
(757)-385-4131
Department Contact
Public Works
Katie E Shannon P.E.
(757)-385-4131
Schedule of Activities
Code
Description
|
Approved Budget Start
Approved Budget End
Approved Budget Cost
|
Current Estimates Start
Current Estimates End
Current Estimates Cost
2000
Design
09/01/2013
03/31/2022
2,760,939
09/01/2013
06/01/2024
2,834,113
3000
Site Acquisition
07/01/2015
03/31/2021
9,178,037
03/15/2022
05/03/2023
8,247,309
4000
Private Utility Adjustments
04/01/2021
03/31/2022
2,000,000
11/16/2022
06/30/2024
2,103,050
5000
Construction
04/01/2022
11/30/2024
24,933,086
01/25/2025
03/22/2028
33,053,356
6000
Street Lights
12/01/2024
04/30/2025
1,970,304
07/23/2026
12/09/2026
2,258,417
7000
Landscaping
05/01/2025
08/31/2025
495,460
12/10/2026
03/31/2027
566,589
9000
Contingencies
09/01/2013
08/31/2025
2,739,885
09/01/2013
03/31/2028
4,340,372
Overall
Project Start, End & Cost:
09/01/2013
08/31/2025
44,077,711
09/01/2013
03/31/2028
53,403,206
Current Status and Progress
100% design plans were submitted on September 8th, 2021 and review is complete. Comment Resolution meetings have been held as of 2/16/2022. Continuation of design to the PS&E will begin 2/2022.
Last updated: 02/15/2022 02:52:30 PM