2.419.000: Centerville Turnpike Phase III

Description and Scope
CIP Section:   Roadways
CIP Status:   Approved Active
Project Type:   New Facility Construction/Expansion
First Year in CIP:  
Business Area:  
  
City District(s):   Centerville

VDOT UPC #109381. City Council identified this project as a Council Initiative under the Goal Improve the Transportation System in the 2018 Annual Report to City Council. This project is for the construction of a four-lane divided highway between Kempsville Road and Lynnhaven Parkway. The project will provide on and off road bike accommodations. The total distance is approximately 1.15 miles. Existing aerial utilities will be relocated to a new overhead location.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager¬†¬† Public Works  Laurie E Murphy P.E. (757)-385-4131

Schedule of Activities
CodeDescription Approved Budget StartApproved Budget EndApproved Budget Cost Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
2000 Design 07/01/2017 10/31/2023 2,158,233 07/15/2017 07/23/2024 2,437,874
3000 Site Acquisition 07/01/2020 07/31/2022 6,670,000 11/14/2023 11/11/2024 5,242,098
4000 Private Utility Adjustments 07/01/2021 10/31/2023 1,480,000 09/10/2024 09/23/2025 1,480,000
5000 Construction 11/01/2023 10/31/2025 27,542,155 04/07/2026 08/10/2028 31,241,611
6000 Street Lights 11/01/2025 01/31/2026 800,000 08/11/2026 02/05/2027 920,000
7000 Landscaping 02/01/2026 05/31/2026 284,945 02/08/2027 08/05/2027 327,687
9000 Contingencies 07/01/2017 05/31/2026 3,893,533 07/15/2017 08/02/2028 3,796,371
OverallProject Start, End & Cost:07/01/201705/31/202642,828,86607/15/201708/10/202845,445,641

Map for Centerville Turnpike Phase III
Current Status and Progress
The website for the Virtual Public Meeting is still accessible at www.centervilleturnpikephase3.com. There is a prerecorded presentation, interactive map showing the project, project documents, schedule, and budget. The Public Hearing has been held . The noise wall voting has concluded.
Last updated: 11/12/2021 09:36:22 AM