City of Virginia Beach, VA
Public Works
Capital Project Detail Sheet

2.414.000: Shipps Corner Road Improvements

Description and Scope
CIP Section:   Roadways
CIP Status:   Approved Active
Project Type:   New Facility Construction/Expansion
First Year in CIP:  
Business Area:  
  
City District(s):   Rose Hall, Undefined

This project is for construction of improvements to Shipps Corner Road from Skylark Drive to the bridge over West Neck Creek. Construction includes drainage improvements, geometric improvements, pedestrian improvements, and installing a left-turn lane from Shipps Corner Road into Cardinal Estates.
This project is for construction of improvements to Shipps Corner Road from Skylark Drive to London Bridge Road. These improvements include access management, turn lane, geometric improvements, bike accommodations, and pedestrian improvements.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager   Public Works  Laurie E Murphy P.E. (757)-385-4131
Department Contact   Public Works  Chris B Cahoon (757)-385-4131
Department Contact   Public Works  Jessica M Thompson (757)-385-4131

Schedule of Activities
CodeDescription|Approved Budget StartApproved Budget EndApproved Budget Cost|Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
2000 Design 03/01/2014 11/30/2018 327,150 03/01/2014 12/30/2022 427,870
3000 Site Acquisition 10/28/2015 11/30/2018 406,168 10/01/2015 09/01/2021 406,168
4000 Private Utility Adjustments 12/01/2019 08/31/2020 285,000 07/01/2028 04/01/2028 420,930
5000 Construction 09/01/2020 08/31/2021 1,337,184 08/01/2029 11/01/2030 1,897,473
6000 Street Lights 09/01/2021 12/31/2021 84,000 10/02/2023 01/02/2024 84,000
7000 Landscaping 01/01/2022 03/31/2022 58,138 01/03/2024 03/30/2024 58,138
9000 Contingencies 03/01/2014 03/31/2022 281,410 03/01/2014 11/01/2030 231,840
OverallProject Start, End & Cost:03/01/201403/31/20222,779,05003/01/201411/01/20303,526,419

Map for Shipps Corner Road Improvements
Current Status and Progress
Updating the 100% plan design to meet VSMP and Contracts requirements. A new Work Order has been processed for post-design and construction activities. 100% Revised plans were submitted on 12/21/21. Comments are due on 1/31/22. Construction of the roadway is scheduled for 4/2023.
Last updated: 02/15/2022 02:53:32 PM