9.006.000: Winston-Salem Avenue Improvements

Description and Scope
CIP Section:   Economic and Tourism Development
CIP Status:   Approved Active
Project Type:   New Facility Construction/Expansion
First Year in CIP:  
Business Area:  
  
City District(s):   Beach

This project will provide funding for design and construction of a two-lane roadway with the potential for on-street parking and wide sidewalks within a fifty foot right-of-way along Winston-Salem Avenue between Pacific Avenue and Mediterranean Avenue. In addition the storm system and public utilities (water and sewer) will be improved.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager   Public Works  Denis U. Ozowara (757)-385-4131
Department Contact   Public Works  Michael _ Tippin P.E. (757)-385-4131

Schedule of Activities
CodeDescription Approved Budget StartApproved Budget EndApproved Budget Cost Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
2000 Design 07/01/2013 10/30/2020 700,000 07/01/2013 07/01/2022 700,000
3000 Site Acquisition 10/01/2019 10/01/2020 275,000 08/30/2021 05/01/2022 325,000
4000 Private Utility Adjustments 10/01/2020 05/30/2022 1,000,000 10/01/2022 04/01/2025 1,000,000
5000 Construction 10/01/2020 05/30/2022 5,005,000 10/01/2022 04/01/2025 5,605,000
6000 Street Lights 01/01/2022 05/30/2022 235,000 10/01/2024 04/01/2025 235,000
7000 Landscaping 02/01/2022 05/30/2022 155,000 10/01/2024 04/01/2025 155,000
9000 Contingencies 07/01/2013 05/30/2022 950,000 07/01/2013 04/01/2025 900,000
OverallProject Start, End & Cost:07/01/201305/30/20228,320,00007/01/201304/01/20258,920,000

Map for Winston-Salem Avenue Improvements
Current Status and Progress
The design team will continue to advance the plans to FINAL design and be ready for the start of construction. Anticipate start of construction October 2020.
Last updated: 12/17/2019 05:05:14 PM