Capital Project Detail Sheet

2.033.000: Princess Anne Road Phase VII-A

Description and Scope
CIP Section:   Roadways
CIP Status:   Approved Active
Project Type:   New Facility Construction/Expansion
First Year in CIP:  
Business Area:  
  
City District(s):   Princess Anne

This project is for the construction of safety improvements on Princess Anne Road from Seaboard Road to Sandbridge Road, including but not limited to, shoulder widening, drainage improvements, and utility relocations.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager   Public Works  Ryan A Johnson (757)-385-4131
Department Contact   Public Works  Ryan A Johnson (757)-385-4131

Schedule of Activities
CodeDescription|Approved Budget StartApproved Budget EndApproved Budget Cost|Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
2000 Design 12/01/2013 06/30/2028 780,060 12/01/2022 07/01/2030 816,210
3000 Site Acquisition 07/01/2026 06/30/2027 900,000 07/01/2028 06/01/2029 900,000
4000 Private Utility Adjustments 07/01/2027 06/30/2028 482,000 07/01/2029 06/01/2030 544,140
5000 Construction 07/01/2028 07/31/2029 4,820,000 07/01/2030 07/01/2032 5,441,400
6000 Street Lights 08/01/2029 10/31/2029 380,400 08/01/2029 10/01/2029 380,400
7000 Landscaping 11/01/2029 04/30/2030 241,000 11/01/2029 04/01/2030 241,000
9000 Contingencies 12/01/2013 04/30/2030 1,140,519 12/01/2013 07/01/2032 1,155,263
OverallProject Start, End & Cost:12/01/201304/30/20308,743,97912/01/201307/01/20329,478,413

Map for Princess Anne Road Phase VII-A
Current Status and Progress
Project currently on hold due to funding
Last updated: 02/15/2022 08:17:31 AM