City of Virginia Beach, VA
Public Works
Capital Project Detail Sheet

2.072.000: First Colonial Rd & VA. Beach Blvd. Intersection Imp.

Description and Scope
CIP Section:   Roadways
CIP Status:   Approved Active
Project Type:   New Facility Construction/Expansion
First Year in CIP:   2000-2001
Business Area:  
  
City District(s):   Beach

This project will improve the First Colonial Road/Virginia Beach Boulevard Intersection by the addition of turn lanes and traffic signalization improvements. This project will include widening of First Colonial Road from Oceana Boulevard to the I-264 overpass from four to six lanes. The additional lane on each side of the roadway will provide for continuous right turn movements.

Points of Contact
Contact TypeCompanyContact PersonPhone
Project Manager   Public Works  Christina L. Ammens (757)-385-4131
Site Acquisition Manager   Public Works  Chris B Cahoon (757)-385-4131
Department Contact   Public Utilities  John D McDonald (757)-385-4631

Schedule of Activities
CodeDescription Approved Budget StartApproved Budget EndApproved Budget Cost Current Estimates StartCurrent Estimates EndCurrent Estimates Cost
2000 Design 01/01/2003 05/31/2019 1,241,620 01/01/2003 02/01/2021 1,341,620
3000 Site Acquisition 06/01/2007 02/28/2018 15,265,485 06/01/2007 02/01/2018 10,847,072
4000 Private Utility Adjustments 05/01/2019 01/31/2020 1,213,738 05/01/2019 03/01/2022 1,213,738
5000 Construction 05/01/2020 05/31/2023 11,194,300 05/01/2022 11/01/2025 18,608,112
6000 Street Lights 01/01/2023 05/31/2023 441,402 06/01/2024 09/01/2024 484,215
7000 Landscaping 02/01/2023 05/31/2023 357,351 06/01/2024 09/01/2024 357,351
9000 Contingencies 01/01/2003 05/31/2023 1,199,305 01/01/2003 11/01/2025 2,033,974
OverallProject Start, End & Cost:01/01/200305/31/202330,913,20101/01/200311/01/202534,886,082

Map for First Colonial Rd & VA. Beach Blvd. Intersection Imp.
Current Status and Progress
Project advertised for Bid on November 7th, 2021. Pre-Bid Meeting is scheduled for December 7th, 2021 at 10 am. Bid opening is on January 11th, 2022 at 3 pm. Private utility relocation to be performed through Spring 2022. Construction is scheduled to start in Spring 2022.
Last updated: 11/15/2021 09:44:10 AM

Attachments
Citizen Information Meeting Advertisement   (32.49 KB pdf)

Related Projects
2.156.000   Laskin Road Phase I-B
2.833.000   First Colonial Rd.- Ph III & Oceana Blvd. (VDOT)
2.833.002   First Colonial Road / Oceana Blvd. "Northern End"